Rate Analysis of Reinforced Concrete Structures

Data required for RCC Rate Analysis:
1. Estimation of materials: Material estimation include
sand, cement, coarse aggregate and steel for a particular mix design. Let us
consider a mix design of 1:1.5:3 for our estimation practice. The dry volume of
total materials required is considered as 1.54 times the wet volume of
concrete, due to voids present in sand and aggregates in dry stage. Therefore,
for our calculation, we will consider the total volume of materials required as
1.54 m3 for 1 m3 of wet concrete.
a) Bags of cement required:
Volume of cement required
for 1m3 of Concrete =1.54/5.50
=0.28 m3
Then number of bags of
cement (volume of one bag of cement = 0.0347 m3)
=0.28×0.0347= 8.07 bags of
cement.
b) Volume of Sand required:
Volume of sand required
=1.5×0.28 = 0.42 m3 of sand.
c) Volume of Coarse
Aggregate Required
Volume of Coarse Aggregate
=3×0.28= 0.84 m3 of coarse aggregates.
d) Estimation of Reinforced
Steel:
Quantity of steel required
depends on components of structure, i.e. slabs, beams, columns, foundations,
roads etc. To estimate the steel required, there are two methods.
First method is, when we
have the drawing available, we can calculate the total weight of steel required
divided by total volume of concrete for different components. This will give us
the weight of reinforcement steel per cubic meter of concrete.
Second method is assuming
the percentage of reinforcement for different components. Following are the
percentage of reinforcement steel generally required per different components.
Its values can vary from structure to structure, and can be assumed from past
experiences of similar structure.
For slabs = 1.0 % of
concrete volume.
For Beam = 2 % concrete volume.
For column = 2.5 % of concrete volume.
For RCC Roads, 0.6% concrete volume.
For Beam = 2 % concrete volume.
For column = 2.5 % of concrete volume.
For RCC Roads, 0.6% concrete volume.
Lets take example of RCC
Column, where reinforcement required is 2.5% of concrete volume, weight of
steel required will be:
=196.25 kg.
2. Labour Requirement for
1m3 of RCC:
Labours required are
presented in terms of days required by particular labour to complete its work
for the given quantity of concrete. Following are the various labours required:
a) Mason: As per Standard
Schedule of Rates and Analysis of Rates, One mason is required for 0.37 days.
b) Labours: One Unskilled
labours required for 3.5 days.
c) Water carrier: One water
carrier required for 1.39 days.
d) Bar Bender: Bar bender
requirement depends on weight of reinforcement. Lets consider one bar bender
required for 100 kg of steel as for 1 day.
e) Mixer Operator: One mixer
operator required for 0.0714 days.
f) Vibrator Operator: One
vibrator operator required for 0.0714 days.
3. Equipments and sundries:
Equipment and other
charges, such as water charges, miscellaneous items, tools and tackles etc can
be assumed as some percentage of total cost of materials and labours. Lets say
it as 7.5%.
4. Contractor’s Profit:
Contractor’s profit depends
on place to place, organization to organization and work to work. It varies
from 10 – 20%. For our case lets assume it as 15% of total cost of materials,
labours and equipments.
We have calculated the
quantity of every item in above 1 – 3 steps. For rate analysis of RCC, we need
to multiply each quantity with their rates to get the amount for every item of
work. Rates vary from place to place and time to time. It is advisable to
assume local rates or standard rates of the place.
The
sum total of all the four items above will give the rate or cost for 1m3 of
concrete.
Comments
Post a Comment